Adani-run Mumbai airport to redevelop T1B from Jan 2027, 9% traffic to be affected


Adani Airport Holdings Limited (AAHL)-operated Mumbai International Airport Limited will commence redevelopment work on the North Section of Terminal 1B from January 2027. Safety concerns linked to the airport’s nearly 60-year-old infrastructure have led to plans for a phased reconstruction of the terminal.

Mumbai Airport handles around 55 million passengers annually, but only about 5 million passengers, or roughly 9 per cent of the total, will be temporarily affected by the de-operationalisation. To maintain continuity and reduce inconvenience, AAHL has given airlines the option of shifting their operations temporarily to Navi Mumbai International Airport, depending on their requirements.

AAHL said it would assist airlines throughout the transition and provide the necessary support to ensure that the movement of services takes place smoothly.

AAHL CEO Arun Bansal said about 91 per cent of Mumbai Airport’s passenger traffic would continue without disruption while the ageing infrastructure undergoes redevelopment. He said only the North Section of Terminal 1B, which represents around one-third of T1’s overall capacity, would be demolished during the first phase to limit the impact on passengers and airport operations. He also clarified that any shift of services to Navi Mumbai Airport would be temporary and would not amount to a permanent transfer of Mumbai Airport traffic.

Terminal 1 has for years been regarded as a safety concern, with authorities relying on temporary measures because there was previously no practical alternative for airlines and passengers.

The risks associated with continuing to operate the terminal have become more significant following the fire at Terminal 1 in April this year. With Navi Mumbai International Airport now operational and available as an alternative for travellers and airlines, the planned closure and phased demolition of T1 can no longer be postponed, AAHL said.

Redevelopment of Terminal 1 is scheduled to begin in January 2027 and is expected to raise its annual passenger handling capacity by 33 per cent, from the current 15 million passengers to 20 million.

Bansal said extensive discussions with airlines regarding the future of Terminal 1 had been taking place since 2020. The proposed redevelopment was also presented to the Airports Economic Regulatory Authority of India (AERA) and later incorporated into the approved tariff framework. While acknowledging concerns raised by some airlines, he stressed that passenger safety had to take priority and that further postponement could affect the safety and convenience of millions of travellers.

Navi Mumbai International Airport is offering a complete waiver of landing charges for new international flights. It also plans to provide cash vouchers to international passengers to help compensate for the difference in User Development Fees (UDF) between Navi Mumbai and Mumbai airports.

The new Navi Mumbai airport is a modern facility equipped with the infrastructure and capacity required to accommodate additional passenger traffic shifted from Mumbai Airport.

According to Bansal, the availability of Navi Mumbai Airport makes it possible to carry out Mumbai Airport’s Terminal 1 redevelopment in stages rather than shutting the entire terminal at once, thereby reducing disruption for both airlines and passengers.

Mumbai Airport and Navi Mumbai International Airport are expected to operate as complementary facilities, together addressing the significant limitations in aviation infrastructure across India’s commercial capital region.


 